Case Background:
Large equipment weighing over 100 tons was successfully loaded onto a ship at the designated dock via a combination of road and barge. Due to the large size and heavy weight of the equipment, the related procedures were quite complex and required a high level of expertise from the personnel. After receiving the cargo information from the client, our team conducted a detailed analysis and professional assessment, providing the client with the best operational plan to ensure the smooth loading and delivery of the equipment.
Basic Information:
Transportation mode: Road + Barge FOB, Dongguan International Container Terminal
POL: DONGGUAN,
POD:TAIWAN
Cargo dimensions: 5914*4975*5021mm 70000KG
Process and difficulties:
After being hoisted and secured at the Foshan factory, the goods were loaded onto hydraulic pallet trucks and transported to the Foshan port.
Challenge: Using two 350-ton truck cranes simultaneously to load ships in Foshan.
Foshan Wharf Barge to Dongguan Humen Wharf
Challenge: Direct loading of a 350-ton floating crane barge onto a large ship.